The University and the Net Zero Energy Project contractor, Vital Energi, have programmed the following work to reduce disruption to our campus community as far as possible. We apologise for any disruption the work may cause you.
Last updated: Friday 26 June 2026.
Programme of works
The Net Zero Energy Project includes three elements of work. Further details, including current and upcoming works and how they may affect you, can be found below.
November 2024 - Early 2027: Construction of a new energy centre on the outer edge of .
District Heat Network
November 2024 - December 2025: Expansion of the District Heat Network.
Building Connections
June 2025 - November 2026: Connecting buildings to the expanded District Heat Network, which will be fed by the new Energy Centre 2. This work will involve fixing district heating pipework to the facade of buildings and bringing the pipework into plant rooms and kitchens. Internal upgrades will also take place, including the replacement of existing gas boilers with new, more efficient systems.
Campus wide
Campus wide accordion
From Monday 22 June to Friday 3 July 2026, the Net Zero Energy Project contractor, Vital Energi, will be carrying out minor leak repairs to the campus district heating pipework.
Work will take place at three locations:
To the west of Lancaster Square on North Campus
Between Pendle College residences, House 24 Winewall and House 27 Crowtrees on Alexandra Park
The corner of Barker House Avenue to the rear of Barker House Farm on Alexandra Park
Minor excavations will be carried out to access and repair the buried pipework, causing some localised disruption, but access routes and deliveries will not be affected. The works are expected to take approximately three to four days to complete at each location.
From Monday 6 July until late August 2026, the Net Zero Energy Project contractor, Vital Energi, will be carrying out works to enclose the newly installed external district heating pipework and valves on the façade of buildings. Work will take place at:
Bowland Main
Cartmel College
County College, including County Field and County South
Furness College
Fylde College
Graduate College
Grizedale College
Lonsdale College
Pendle College
How will this work affect you?
Vital Energi contractors will be working outside each building to install protective covers around the pipework and valves.
There will be short periods of drilling noise while the covers are fixed to the external wall of each building.
Work will progress between 8am – 6pm (Monday to Friday).
Dates can be subject to change.
North Campus
North Campus accordion
The Net Zero Energy Project contractor, Vital Energi, will be working on the connection of the County Field residential buildings to the campus District Heat Network. This will involve internal and external works at the following houses.
House 78 Sloe
Erection of scaffolding to the gable end of the building: 6 July – 10 July 2026
Final connection of the district heating pipework into the building: 20 July – 22 July 2026
Replacement of the existing boilers with a new heating and hot water system in the communal stairwell: 20 July – 22 July 2026
House 79 Damson
Final connection of the district heating pipework into the building: 20 July – 22 July 2026
Replacement of the existing boilers with a new heating and hot water system in the communal stairwell: 20 July – 22 July 2026
House 80 Hawthorn
Final connection of the district heating pipework into the building: 20 July – 24 July 2026
Replacement of the existing boilers with a new heating and hot water system in the communal stairwell: 22 July – 24 July 2026
House 91 Primrose
Final connection of the district heating pipework into the building: 27 July – 29 July 2026
Replacement of the existing boilers with a new heating and hot water system in the communal stairwell: 27 July – 29 July 2026
House 92 Orchid
Final connection of the district heating pipework into the building: 29 July – 31 July 2026
Replacement of the existing boilers with a new heating and hot water system in the communal stairwell: 29 July – 31 July 2026
House 93 Nettle
Final connection of the district heating pipework into the building: 3 August – 5 August 2026
Replacement of the existing boilers with a new heating and hot water system in the communal stairwell: 3 August – 5 August 2026
House 94 Mallow
Erection of scaffolding to the gable end of the building: 6 July – 10 July 2026
Final connection of the district heating pipework into the building: 5 August – 7 August 2026
Replacement of the existing boilers with a new heating and hot water system in the communal stairwell: 5 August – 7 August 2026
House 101 Aconite
Erection of scaffolding to the gable end of the building: 6 July – 10 July 2026
House 106 Foxglove
Final connection of the district heating pipework into the building: 10 August – 12 August 2026
Replacement of the existing boilers with a new heating and hot water system in the communal stairwell: 10 August – 12 August 2026
How will this work affect you?
During the scaffolding works:
Seven parking spaces will be temporarily closed on the morning of 6 July for the delivery of scaffolding.
The on the perimeter roadside of House 94 Mallow and the to the north of House 81 Zostera will be fenced off and used as scaffolding laydown areas.
Pedestrian routes will remain open and access to all building entrances will be maintained.
Scaffolding will remain in place until all works are complete and will be dismantled by the end of August.
Work will take place after 10am on Monday 6 July to allow for departures and will then revert to contracted hours 8am – 6pm (Monday to Friday) and will be noisy at times. No work will take place during graduation week.
During the external and internal works:
Hot water will be turned off at 8.30am on day one and is expected to remain off until the work is completed on day three. The cold water supply will not be affected in occupied accommodation.
Vital Energi contractors will be accessing the communal stairwells but won’t need access to any student flats.
Access in and out of all accommodation will be maintained.
Work will take place between 8.30am – 5.30pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.?If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, will be working on the connection of the County Main Family Flats to the campus District Heat Network. This will involve internal works at the following flats.
Flat 17
Replacement of the existing boiler with a new heating and hot water system in kitchen: 17 August – 21 August 2026
Flat 18
Replacement of the existing boiler with a new heating and hot water system in kitchen: 20 August – 26 August 2026
Flat 19
Replacement of the existing boiler with a new heating and hot water system in kitchen: 25 August – 1 September 2026
Flat 20
Replacement of the existing boiler with a new heating and hot water system in kitchen: 28 August – 4 September 2026
Flat 21
Replacement of the existing boiler with a new heating and hot water system in kitchen: 3 September – 9 September 2026
Flat 22
Replacement of the existing boiler with a new heating and hot water system in kitchen: 8 September – 14 September 2026
Flat 23
Replacement of the existing boiler with a new heating and hot water system in kitchen: 1 September – 7 September 2026
Flat 24
Replacement of the existing boiler with a new heating and hot water system in kitchen: 8 September – 14 September 2026
Flat 25
Replacement of the existing boiler with a new heating and hot water system in kitchen: 17 August – 21 August 2026
Flat 26
Replacement of the existing boiler with a new heating and hot water system in kitchen: 24 August – 28 August 2026
Flat 27
Replacement of the existing boiler with a new heating and hot water system in kitchen: 23 June – 25 June 2026
How will this work affect you?
Up to three Vital Energi contractors will require access through the building and the communal areas within student flats. There may be some localised disruption while deliveries take place.
Access in and out of all accommodation will be maintained.
Hot water will be turned off at 8.30am on day one and is expected to remain off until the work is completed on day three. The cold water supply will not be affected in occupied accommodation.
Work will take place between 8.30am – 5.30pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact. If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
From Friday 19 June to late August 2026, the Net Zero Energy Project contractor, Vital Energi, will be working on the installation of external district heating pipework to the southwest façade of the County Main building.
Scaffolding will be erected at the and on the roof of the building to allow the new pipework to be installed and connected to the rooftop flats. Vital Energi contractors will be working at height outside the kitchen windows of the accommodation on C and D Floors, and it is advised that blinds are left closed for privacy.
The pedestrian area to the east of the building will be closed off while high level access machinery and a temporary staircase are in place to enable the contractor to safely deliver scaffolding materials to roof level.
The contractors may use the inside the building very occasionally but won't need access to any student flats. Once the scaffold staircase to the east of the building is erected, this will negate the need to access the building internally.
Access will be closed along the from County Avenue into Lancaster Square throughout the works. An accessible diversion route and signage will be in place.
Seven parking spaces on the will be fenced off for a storage area. The spaces will reopen from Monday 13 July to Friday 17 July for Graduation and will close again until the work is completed. The electric vehicle parking will remain open throughout the work.
Access to the County South kitchens, bin stores and cycle parking will remain open from County Avenue.
Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.?If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
Until early July 2026, the Net Zero Energy Project contractor, Vital Energi, will be working on the replacement of the existing boilers with a district heating pipework connection from the Bowland Main plant room into the Welcome Centre rooftop plant room.
Three will be out of use on Bowland Avenue for a Vital Energi compound.
Scaffolding will be erected . Access to the and the through to Bowland Main quad will remain open.
The will be out of use. Alternative cycle parking is located outside and on .
Bin stores will remain open.
Work will progress between 8am – 5pm (Monday to Friday) and will be noisy at times. The project webpages list?alternative study spaces?if required.
Dates can be subject to change.
South Campus
South Campus accordion
The Net Zero Energy Project contractor, Vital Energi, will be working on the connection of the Fylde College residential buildings to the campus District Heat Network. This will involve internal and external works at the following houses.
House 68 Lytham
Pressure testing and flushing of pipework in plant room: between 18 May – early July 2026
Commissioning of the new district heating system in plant room: 1 July – 2 July 2026
House 69 Pilling
Pressure testing and flushing of pipework in plant room: between 18 May – early July 2026
Commissioning of the new district heating system in plant room: 3 July – 6 July 2026
How will this work affect you?
Vital Energi contractors will be using the communal stairwells to access plant rooms on the top floor of the houses but?won’t?need access to any student flats.
Work will take place between 8.30am – 5.30pm (Monday to Friday)?and is not expected to be noisy. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.?If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, will be working on the connection of InfoLab21 to the campus District Heat Network.
Replacement of the boilers and?pipework connections in plant room: 18 June - early August 2026
Commissioning of the new district heating system in plant room: 6 August - late August 2026
How will this work affect you?
Vital Energi contractors will be accessing the plant room externally and won’t require internal access to the building.
Work will take place between 8am – 6pm (Monday to Friday)?and will be noisy at times. The project webpages list?alternative study spaces?if?required.
Dates can be subject to change.
From Monday 30 March to August 2026, the Net Zero Energy Project contractor, Vital Energi, will be installing new pipework on the to enable new district heating connections into the building.
Work will progress between 8am - 6pm (Monday to Friday).
Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, will be working on the connection of the Grizedale College residential buildings to the campus District Heat Network. This will involve internal and external works at the following houses.
Houses 107 to 111 and 117 to 129
House 107 Sawrey
Replacement of the boilers with a new heating and hot water system in communal stairwells: 8 July – 10 July 2026
House 108 Tarn Hows
Replacement of the boilers with a new heating and hot water system in communal stairwells: 8 July – 10 July 2026
House 109 Finsthwaite
Replacement of the boilers with a new heating and hot water system in communal stairwells: 13 July – 15 July 2026
House 110 Brathay
Replacement of the boilers with a new heating and hot water system in communal stairwells: 15 July – 17 July 2026
House 111 Tilberthwaite
Replacement of the boilers with a new heating and hot water system in communal stairwells: 20 July – 22 July 2026
House 117 Townen
Replacement of the boilers with a new heating and hot water system in communal stairwells: 20 July – 22 July 2026
House 118 Satterthwaite
Replacement of the boilers with a new heating and hot water system in communal stairwells: 22 July – 24 July 2026
House 119 Bessy Bank
Replacement of the boilers with a new heating and hot water system in communal stairwells: 27 July – 29 July 2026
House 120 Force Forge
Replacement of the boilers with a new heating and hot water system in communal stairwells: 29 July – 31 July 2026
House 121 Blawith
Replacement of the existing boilers with a new heating and hot water system in communal stairwells: 3 August – 5 August 2026
House 122 Graythwaite
Replacement of the existing boilers with a new heating and hot water system in communal stairwells: 5 August – 7 August 2026
House 123 Newby
Replacement of the existing boilers with a new heating and hot water system in communal stairwells: 10 August – 12 August 2026
House 124 Rusland
Replacement of the existing boilers with a new heating and hot water system in communal stairwells: 12 August – 14 August 2026
House 125 Whinfell
Replacement of the existing boilers with a new heating and hot water system in communal stairwells: 17 August – 19 August 2026
House 126 Storrs
Replacement of the existing boilers with a new heating and hot water system in communal stairwells: 19 August – 21 August 2026
House 127 Sweetenthwaite
Replacement of the existing boilers with a new heating and hot water system in communal stairwells: 24 August – 26 August 2026
House 128 Lowick
Replacement of the existing boilers with a new heating and hot water system in communal stairwells: 26 August – 28 August 2026
House 129 Brow Edge
Replacement of the existing boilers with a new heating and hot water system in communal stairwells: 1 September – 3 September 2026
How will this work affect you?
Hot water will be turned off at 8.30am on day one and is expected to remain off until the work is completed on day three. The cold water supply will not be affected in occupied accommodation.
Vital Energi contractors will be accessing the communal stairwells but won’t need access to any student flats.
Access in and out of all accommodation will be maintained.
Scaffolding is in place to allow Vital Energi contractors to access plant rooms.
Work will take place between 8.30am – 5.30pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.?If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
Houses 112 to 116
Houses 112-113 Skelwith and High Cross
Replacement of the boilers and pipework connections in plant room: 29 June – early August 2026
Hot water interruption: 8 July 2026
Commissioning of the new district heating system and boiler removal in plant room: 5 August – mid August 2026
Houses 114-115 Sunnybank and Carron Crag
Replacement of the boilers and pipework connections in plant room: 22 July – late August 2026
Hot water interruption: 29 July 2026
Commissioning of the new district heating system and boiler removal in plant room: 27 August – mid September 2026
House 116 Nibthwaite
Replacement of the boilers and pipework connections in plant room: 14 August – late September 2026
Hot water interruption: 21 August 2026
Commissioning of the new district heating system and boiler removal in plant room: 22 September – mid October 2026
How will this work affect you?
There will be no hot water on one day only, for a maximum of eight hours in each house during the replacement of the boilers. This is expected to take place between 9am – 5pm.
Scaffolding is in place to allow Vital Energi contractors to access plant rooms. They won't need access to any student flats.
Some pedestrian access routes in the local area are closed. Diversion signage is in place and building entrances will be maintained at all times.
Work will progress between 8.30am – 5.30pm (Monday to Friday) and will be noisy at times. The project webpages list?alternative study spaces?if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.?If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
A one-way system is in place northbound along South Drive from the up to to enable the contractor to construct the new energy centre. This one-way system will be in place until the project completes in Spring 2027.
A new entrance has been created from George Fox Avenue into and a contractor's compound has been created on the east side of the main car park. The west side of George Fox car park will remain in use for using the new entrance/exit from George Fox Avenue.
Alexandra Park
Alexandra Park accordion
The Net Zero Energy Project contractor, Vital Energi, will be working on the connection of the Cartmel College residential buildings to the campus District Heat Network. This will involve internal and external works at the following houses.
Houses 46, 52, 54 and 55
House 46 Bigland
Pressure testing and flushing of pipework in plant room: between 18 May – early July 2026
Replacement of boilers and pipework connections in plant room: 29 June – early August 2026
Hot water interruption: 9 July 2026 (also affects Houses 47 to 49)
Commissioning of the new district heating system and boiler removal in plant room: 7 August – late August 2026
House 52 Haverthwaite
Pressure testing and flushing of pipework in plant room: between 18 May – early July 2026
Replacement of boilers and pipework connections in plant room: 24 July – early September 2026
Hot water interruption: 6 August 2026 (also affects Houses 50 to 51)
Commissioning of the new district heating system and boiler removal in plant room: 4 September – late September 2026
House 54 Grange
Pressure testing and flushing of pipework in plant room: between 18 May – early July 2026
Replacement of boilers and pipework connections in plant room: 2 September – late October 2026
Hot water interruption: 11 September 2026 (also affects House 53)
Commissioning of the new district heating system in plant room: 26 October – mid November 2026
House 55 Braystones Tarn
Pressure testing and flushing of pipework in plant room: between 18 May – early July 2026
Replacement of boilers and pipework connections in plant room: 11 September – late October 2026
Hot water interruption: 7 October 2026 (also affects House 56)
Commissioning of the new district heating system: 26 October – mid November 2026
How will this affect you?
There will be no hot water on one day only, for a maximum of eight hours in each house during the replacement of the boilers. This is expected to take place between 9am – 5pm.
Vital Energi contractors will be using the communal stairwells to access the plant rooms on the top floor of the houses but?won’t?need access to any student flats.
Work will take place between 8.30am – 5.30pm (Monday to Friday). There will be localised noise during the boiler removal. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.?If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
Family Flats, Houses 158 to 162 Lyth
Houses 158A and 158B
Replacement of the existing boilers with a new heating and hot water system in kitchen, including builders work: 8 July – 10 July 2026
Houses 159A and 159B
Replacement of the existing boiler with a new heating and hot water system in kitchen, including builders work: 13 July – 15 July 2026
Houses 160A and 160B
Replacement of the existing boiler with a new heating and hot water system in kitchen, including builders work: 15 July – 17 July 2026
Houses 161A and 161B
Replacement of the existing boiler with a new heating and hot water system in kitchen, including builders work: 20 July – 22 July 2026
Houses 162A and 162B
Replacement of the existing boiler with a new heating and hot water system in kitchen, including builders work: 22 July – 24 July 2026
Family Flats, Houses 163 to 168 Backbarrow
Houses 163A and 163B
Replacement of the existing boiler with a new heating and hot water system in kitchen, including builders work: 5 August – 7 August 2026
Houses 164A and 164B
Replacement of the existing boiler with a new heating and hot water system in kitchen, including builders work: 10 August – 12 August 2026
Houses 165A and 165B
Replacement of the existing boiler with a new heating and hot water system in kitchen, including builders work: 17 August – 19 August 2026
Houses 166A and 166B
Replacement of the existing boiler with a new heating and hot water system in kitchen, including builders work: 19 August – 21 August 2026
Houses 167A and 167B
Replacement of the existing boiler with a new heating and hot water system in kitchen, including builders work: 1 September – 3 September 2026
Houses 169 to 171 Hayeswater
House 169
Replacement of the existing boiler with a new heating and hot water system in kitchen, including builders work: 2 September – 4 September 2026
House 170
Replacement of the existing boiler with a new heating and hot water system in kitchen, including builders work: 7 September – 9 September 2026
House 171
Replacement of the existing boiler with a new heating and hot water system in kitchen, including builders work: 9 September – 11 September 2026
Houses 172 to 179 Seathwaite
House 172
Replacement of the existing boiler with a new heating and hot water system in kitchen, including builders work: 17 August – 19 August 2026
House 173
Replacement of the existing boiler with a new heating and hot water system in kitchen, including builders work: 19 August – 21 August 2026
House 174
Replacement of the existing boiler with a new heating and hot water system in kitchen, including builders work: 13 July – 15 July 2026
House 175
Replacement of the existing boiler with a new heating and hot water system in kitchen, including builders work: 8 July – 10 July 2026
House 176
Replacement of the existing boiler with a new heating and hot water system in kitchen, including builders work: 1 September – 3 September 2026
House 177
Replacement of the existing boiler with a new heating and hot water system in kitchen, including builders work: 2 September – 4 September 2026
House 178
Replacement of the existing boiler with a new heating and hot water system in kitchen, including builders work: 7 September – 9 September 2026
House 179
Replacement of the existing boiler with a new heating and hot water system in kitchen, including builders work: 9 September – 11 September 2026
How will this affect you?
From Monday 6 July to Tuesday 7 July, scaffolding will be installed to allow external builders work to take place.
Builders work will be carried out on the external wall of each flat or house to allow the pipework to be connected. Once works start, there will be noise for up to 2 hours.
Up to three Vital Energi contractors will require access through the communal areas within student flats. There may be some localised disruption while deliveries take place.
Access in and out of all accommodation will be maintained.
Hot water will be turned off at 8.30am on day one and is expected to remain off until the work is completed on day three. The cold water supply will not be affected in occupied accommodation.
Work will take place between 8.30am – 5.30pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.?If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, will be working on the connection of the Furness College residential buildings to the campus District Heat Network. This will involve internal and external works at the following houses.
House 71 Pennington
Pressure testing and flushing of pipework in plant room: between 18 May – early July 2026
Commissioning of the new district heating system in plant room: 7 July – 8 July 2026
House 72 Colton
Pressure testing and flushing of pipework in plant room: between 18 May – early July 2026
Commissioning of the new district heating system in plant room: 9 July – 10 July 2026
House 74 Hawkshead
Pressure testing and flushing of pipework in plant room: between 18 May – early July 2026
Commissioning of the new district heating system in plant room: 13 July – 14 July 2026
Vital Energi contractors will be using the communal stairwells to access plant rooms on the top floor of the houses but won’t need access to any student flats.
Work will take place between 8.30am – 5.30pm (Monday to Friday) and is not expected to be noisy. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.?If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, will be working on the connection of the Graduate College residential buildings to the campus District Heat Network. This will involve internal and external works at the following houses.
Houses 1 to 11
House 1 Bassenthwaite
Remaining external pipework installation to the façade of the building: 6 July – late July 2026
Replacement of the existing boiler with a new heating and hot water system in bar area: 8 July – 10 July 2026
Flats 1, 3 and 5
Replacement of the existing boilers with a new heating and hot water system in kitchens: 13 July – 15 July 2026
Flats 2, 4 and 6
Replacement of the existing boilers with a new heating and hot water system in kitchens: 15 July – 17 July 2026
House 2 Blea
Remaining external pipework installation to the façade of the building: 20 July – late July 2026
Flats 7, 8 and 9
Replacement of the existing boilers with a new heating and hot water system in kitchens: 20 July – 22 July 2026
House 3 Brotherswater
Remaining external pipework installation to the façade of the building: 6 July – late July 2026
Flats 10, 12 and 14
Replacement of the existing boilers with a new heating and hot water system in kitchens: 20 July – 24 July 2026
Flats 11, 13 and 15
Replacement of the existing boilers with a new heating and hot water system in kitchens: 27 July – 29 July 2026
House 4 Burnmoor
Flats 16, 19 and 22
Replacement of the existing boilers with a new heating and hot water system in kitchens: 29 July – 31 July 2026
Flats 17, 20 and 23
Replacement of the existing boilers with a new heating and hot water system in kitchens: 3 August – 5 August 2026
Flats 18, 21 and 24
Replacement of the existing boilers with a new heating and hot water system in kitchens: 5 August – 7 August 2026
House 5 Buttermore
Flats 25 and 26
Replacement of the existing boilers with a new heating and hot water system in kitchens: 10 August – 12 August 2026
Flats 27 and 28
Replacement of the existing boilers with a new heating and hot water system in kitchens: 12 August – 14 August 2026
House 6 Coniston
Flats 29, 32 and 35
Replacement of the existing boilers with a new heating and hot water system in kitchens: 12 August – 14 August 2026
Flats 30, 33 and 36
Replacement of the existing boilers with a new heating and hot water system in kitchens: 17 August – 19 August 2026
Flats 31, 34 and 37
Replacement of the existing boilers with a new heating and hot water system in kitchens: 19 August – 21 August 2026
House 7 Crummock Water
Remaining external pipework installation to the façade of the building: 17 August – late August 2026
Flats 38, 40, 42 and 44
Replacement of the existing boilers with a new heating and hot water system in kitchens: 24 August – 26 August 2026
Flats 39, 41, 43 and 45
Replacement of the existing boilers with a new heating and hot water system in kitchens: 16 August – 28 August 2026
House 8 Derwentwater
Remaining external pipework installation to the façade of the building: 17 August – early September 2026
Flats 46 to 49
Replacement of the existing boilers with a new heating and hot water system in kitchens: 1 September – 3 September 2026
House 9 Devoke
Replacement of the existing boilers with a new heating and hot water system in cleaners room: 8 July – 10 July 2026
Remaining external pipework installation to the façade of the building: 17 August – early September 2026
Flats 50, 53, 56 and 59
Replacement of the existing boilers with a new heating and hot water system in kitchens: 2 September – 4 September 2026
Flats 51, 54, 57 and 60
Replacement of the existing boilers with a new heating and hot water system in kitchens: 7 September – 9 September 2026
Flats 52, 55 and 58
Replacement of the existing boilers with a new heating and hot water system in kitchens: 9 September – 11 September 2026
House 10 Elterwater
Replacement of the existing boilers with a new heating and hot water system in porters room: 8 July – 10 July 2026
Flats 61 to 64
Replacement of the existing boilers with a new heating and hot water system in kitchens: 14 September – 16 September 2026
House 11 Ennerdale
Replacement of the existing boilers with a new heating and hot water system in study area: 8 July – 10 July 2026
Remaining external pipework installation to the façade of the building: 7 September – mid September 2026
Flats 65 to 68
Replacement of the existing boilers with a new heating and hot water system in kitchens: 16 September – 18 September 2026
How will this work affect you?
During the remaining external pipework installation:
Scaffolding will be erected at one side of each building to allow the new pipework to be installed and connected into the building.
Some pedestrian access routes in the local area will be closed. Diversion signage will be in place and building entrances will be maintained at all times.
During the replacement of the boilers in kitchens:
Up to three Vital Energi contractors will require access through the communal areas within student flats. There may be some localised disruption while deliveries take place.
Access in and out of all accommodation will be maintained.
Hot water will be turned off at 8.30am on day one and is expected to remain off until the work is completed on day three. The cold water supply will not be affected in occupied accommodation.
Work will take place between 8.30am – 5.30pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.?If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
Houses 16, 19, 20 and 21
House 16 Loweswater
Replacement of boilers and pipework connections in plant room: 12 August – late September 2026
Hot water interruption: 26 August 2026 (also affects Houses 12 to 15)
Commissioning of the new district heating system and boiler removal in plant room: 5 October – late October 2026
House 19 Stickle
Pressure testing and flushing of pipework in plant room: between 18 May – early July 2026
Commissioning of the new district heating system and boiler removal in plant room: 30 July – late August 2026
Hot water interruption: complete
House 20 Thirlmere
Replacement of boilers and pipework connections in plant room: 6 May – mid June 2026
Pressure testing and flushing of pipework in plant room: between 18 May – early July 2026
Hot water interruption: complete
Commissioning of the new district heating system and boiler removal in plant room: 20 August – mid September 2026
House 21 Ullswater
Pressure testing and flushing of pipework in plant room: between 18 May – early July 2026
Replacement of boilers and pipework connections in plant room: 4 June – mid July 2026
Hot water interruption: 18 June 2026 (also affects Houses 22 and 23)
Commissioning of the new district heating system and boiler removal in plant room: 11 September – late October 2026
How will this affect you?
There will be no hot water on one day only, for a maximum of eight hours in each house during the replacement of the boilers. This is expected to take place between 9am – 5pm.
Vital Energi contractors will be using the communal stairwells to access plant rooms on the top floor of the houses but?won’t?need access to any student flats.
Work will take place between 8.30am – 5.30pm (Monday to Friday). There will be localised noise during the boiler removal. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.?If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, will be working on the connection of the Grizedale College residential buildings to the campus District Heat Network. This will involve internal and external works at the following houses.
House 30 Easdale Tarn
Pressure testing and flushing of pipework in plant room: between 18 May – early July 2026
How will this work affect you?
Vital Energi contractors will be accessing the communal stairwells but won't need access to any student flats.
Work will take place between 8.30am – 5.30pm (Monday to Friday) and is not expected to be noisy. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.? If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, will be working on the connection of the Lonsdale College residential buildings to the campus District Heat Network. This will involve internal and external works at the following houses.
House 32 Cantsfield
Pressure testing and flushing of pipework in plant room: between 18 May – early July 2026
Replacement of boilers and pipework connections in plant room: 10 August – late August 2026
Commissioning of the new district heating system and boiler removal in plant room: 10 August – early September 2026
House 34 Whittington
Pressure testing and flushing of pipework in plant room: between 18 May – early July 2026
Replacement of boilers and pipework connections in plant room: 15 June – mid August 2026
Hot water interruption: 16 July 2026
Commissioning of the new district heating system and boiler removal in plant room: 13 August – early September 2026
House 35 Beckfoot
Pressure testing and flushing of pipework in plant room: between 18 May – early July 2026
Commissioning of the new district heating system and boiler removal in plant room: 24 August – mid September 2026
House 36 Tunstall
Replacement of boilers and pipework connections in plant room: 13 May – early July 2026
Pressure testing and flushing of pipework in plant room: between 18 May – early July 2026
Hot water interruption: 4 June 2026
Commissioning of the new district heating system and boiler removal in plant room: 20 August – early September 2026
House 37 Wennington
Pressure testing and flushing of pipework in plant room: between 18 May – early July 2026
Commissioning of the new district heating system and boiler removal in plant room: 14 September – mid October 2026
House 39 Barbon
Pressure testing and flushing of pipework in plant room: between 18 May – early July 2026
Replacement of boilers and pipework connections in plant room: 8 July – late August 2026
Hot water interruption: 29 July 2026
Commissioning of the new district heating system and boiler removal in plant room: 26 August – mid September 2026
House 40 Casterton
Pressure testing and flushing of pipework in plant room: between 18 May – early July 2026
Replacement of boilers and pipework connections in plant room: 16 July – late August 2026
Hot water interruption: 30 July 2026 (also affects Houses 41 and 42)
Commissioning of the new district heating system and boiler removal in plant room: 27 August – mid September 2026
House 43 Arkholme
Pressure testing and flushing of pipework in plant room: between 18 May – early July 2026
Replacement of boilers and pipework connections in plant room: 13 August – late September 2026
Hot water interruption: 27 August 2026 (also affects Houses 44 and 45)
Commissioning of the new district heating system and boiler removal in plant room: 5 October – late October 2026
How will this affect you?
There will be no hot water on one day only, for a maximum of eight hours in each house during the replacement of the boilers. This is expected to take place between 9am – 5pm.
Vital Energi contractors will be using the communal stairwells to access plant rooms on the top floor of the houses but?won’t?need access to any student flats.
Work will take place between 8.30am – 5.30pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.?If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
The Net Zero Energy Project contractor, Vital Energi, will be working on the connection of the Pendle College residential buildings to the campus District Heat Network. This will involve internal and external works at the following houses.
House 24 Winewall
Pressure testing and flushing of pipework in plant room: between 18 May – early July 2026
Replacement of boilers and pipework connections in plant room: 18 June – late July 2026
Hot water interruption: 2 July 2026 (also affects Houses 25 and 26)
Commissioning of the new district heating system and boiler removal in plant room: 30 July – late August 2026
House 27 Crowtrees
Pressure testing and flushing of pipework in plant room: between 18 May – early July 2026
Replacement of boilers and pipework connections in plant room: 16 July – early September 2026
Hot water interruption: 6 August 2026 (also affects House 28)
Commissioning of the new district heating system and boiler removal in plant room: 4 September – late September 2026
House 29 Barnoldswick
Pressure testing and flushing of pipework in plant room: between 18 May – early July 2026
Replacement of boilers and pipework connections in plant room: complete
Hot water interruption: complete
Commissioning of the new district heating system in plant room: 27 July – mid August 2026
How will this affect you?
There will be no hot water on one day only, for a maximum of eight hours in each house during the replacement of the boilers. This is expected to take place between 9am – 5pm.
Vital Energi contractors will be using the communal stairwells to access plant rooms on the top floor of the houses but?won’t?need access to any student flats.
Work will take place between 8.30am – 5.30pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact.? If you need any further information in the meantime, please get in touch with them.
Dates can be subject to change.
Contact the Facilities Helpdesk
If you have any questions about the project and work taking place across campus you can contact the Facilities Helpdesk (Mon-Fri 9am-5pm).